CONSTRUCTION UPDATES

Keep up to date with construction progress

Update 2: Maryland Avenue NE, from 2nd St to 11th St., NE, falls under the Historic District. The work under the original contract consists of safety/streetscape improvements along Maryland Avenue NE. 

 

In addition to the DDOT Maryland Avenue project, Washington Gas (a WGL company) is replacing the gas main and upgrading the services to every customer within the project limit. The utility cuts in the sidewalk will result in the deterioration of the existing sidewalk. It is necessary to ensure existing sidewalks, curb, and gutter are upgraded to the Historic District standards. 

 

DDOT has secured additional funds to replace the existing concrete curb, gutter, and PCC sidewalk at Maryland Avenue NE, from 2nd St., NE to 14th St., NE between proposed bump-outs at the intersections and replace with the brick sidewalk, granite curb and brick gutter in the historic district. 

 

This will require additional 139 calendars days to complete the work with new project completion date of October 27, 2021

Update 1: DDOT is issuing a notice to proceed to Fort Myer Construction Corporation for construction on June10, 2019.

Please note that Washington Gas has an ongoing project within the same project area as the Maryland Avenue NE Streetscape project. For more information about that project, visit their website https://www.washingtongas.com