Maryland Ave Community Information
Bi-Weekly Project Update for 04/19/2021 – 05/02/2021








Two Week Look Ahead - DDOT
Transfer to temporary poles (7th to 14th Street).
Install 20Ft SL/TS Poles (7th to 14th Street)
Pulling Electric Cables for communication and streetlight (4th to 14th street)
Work on bump-outs (12th Street and 10th street intersection) (outbound)
Install C& G and Brick Sidewalk (6th to 7th street outbound)
Work on Brick sidewalk (11th street Intersection) (Outbound)
Miss Utility Tickets -Maryland Ave between 14th St to 10th St
PCC Bus Pad at 8th St Intersection, outbound
PCC Bus Pad extension at 7th St Intersection, outbound
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 7th and 14th St)
Traffic light foundations (8th to 14th St)
PCC Base Repairs (B/W 9th and 14th St)
Fire Hydrant @ 5th and C Street
Fire Hydrant (sta.30+69.54) (8th Street Intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
200 Block of Mass Ave NE, Services Installation
200 Block of Mass Ave NE, Continue gas main installation
300 Block of Maryland Ave continue disconnects.
700/800 Block of Maryland Ave continue disconnects.
900/1000 Block of Maryland Ave continue disconnects.
1000/1100 Block of Maryland Ave continue disconnects.
Project Updates – DDOT
Transfer to temporary poles (7th to 14th Street)
Install 20Ft SL/TS Poles (7th to 14th Street)
Pulling Electric Cables for communication and streetlight (4th to 14th street)
Work on bump-outs (12th Street Intersection) (outbound)
Install Granite Curb (12th to 13th street outbound)
Work on Brick sidewalk (11th to 12th Street) (Outbound)
PCC Bus pad installation at Maryland Ave and 12th St intersection (Outbound)
Miss Utility Tickets -Maryland Ave NE between 10th St and 14th St.
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 7th and 14th St)
Traffic light foundations (8th to 14th St)
E. Pipe stubs for Street lights (12 to 13th street)
PCC Base Repairs (B/W 9th and 14th St)
SD Basin connecting pipe I-28 (10th street intersection)