Maryland Ave Community Information
Bi-Weekly Project Update for 05/17/2021 – 05/30/2021
Two Week Look Ahead - DDOT
Transfer to temporary poles (7th to 14th Street).
Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)
Pulling Electric Cables for communication and streetlight (4th to 14th street)
Work on Bump-outs, C & G (Elliot to 14th Street) (outbound)
Work on Brick sidewalk @Elliot to 14th street (Outbound)
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 7th and 14th St)
Traffic/street light foundations (8th to 14th St)
PCC Base Repairs (B/W 8th and 14th St)
Remove and reinstall 18" RCP MH-32 to MH-33
Two Week Look Ahead - Washington Gas and Light Ahead
700 / 800 Block of Maryland Ave and D St continue disconnects.
8th St and Maryland Ave NE continue disconnects
9th St and Maryland Ave NE intersection continue disconnects
4th St & C St NE continue disconnects
8th St and Maryland Ave, multiple locations continue disconnects.
Project Updates – DDOT
Transfer to temporary poles (7th to 14th Street).
Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)
Pulling Electric Cables for communication and streetlight (4th to 14th street)
Work on Bio-retention (Elliot street) (outbound)
Work on Bump-outs (Elliot to 14th Street) (outbound)
Work on Brick sidewalk @7th to 6th street (Inbound)
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 7th and 14th St)
Traffic/street light foundations (8th to 14th St)
PCC Base Repairs (B/W 8th and 14th St)