• Maryland Ave Community Information

Bi-Weekly Project Update for 05/31/2021 – 06/13/2021


Two Week Look Ahead - DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (4th to 14th street)

  • Work on Medians (14th street to 13th street)

  • Work on Brick sidewalk (9th Street) (outbound)

  • Miss Utility Tickets -Maryland Ave NE between 14th St and 6th St

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic/street light foundations (8th to 14th St)

  • PCC Base Repairs (B/W 8th and 14th St)

  • Remove and reinstall 18" RCP MH-32 to MH-33


Two Week Look Ahead - Washington Gas and Light Ahead

  • 4th St & C St NE continue disconnects

  • 260 Maryland Ave, replace gas service


Project Updates – DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (4th to 14th street)

  • Work on Bio-retention (Elliot street) (outbound)

  • Work on Bump-outs (Elliot to 14th Street) (outbound)

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic/street light foundations (8th to 14th St)

  • PCC Base Repairs (B/W 8th and 14th St)











27 views0 comments