• Maryland Ave Community Information

Bi-Weekly Project Update for February 22, 2021-March 7, 2021




Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft SL/TS Poles (7th to 14th Street)

  • Work on bump-outs and straight curb at 11th Street Inbound.

  • Work on Brick sidewalk (11th to 12th Street) (Outbound)

  • Miss Utility Tickets -Maryland Ave NE between 10th St and 14th St.

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic light foundations (8th to 14th St)

  • E. Pipe stubs for Street lights (12 to 13th street)

  • Test Pits (B/w 10th and 14th St)

  • PCC Base Repairs (B/W 7th and 14th St)

  • SD M-38 (13th St intersection)

To Week Look Ahead - Washington Gas and Light Ahead

  • 300 Block of Mass Ave NE. Services Installation

  • 4th St NE between Mass Ave and Maryland Ave, Continue gas main installation.

  • 1100/1200 Block of Maryland Ave continue disconnects.

Project Updates – DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft SL/TS Poles (7th to 14th Street)

  • Work on bump-outs and straight curb (10th and 11th Street) (Outbound)

  • Work on Brick sidewalk (9th to 8th Street) (Outbound)

  • Traffic light foundations (8th to 14th St)

  • PCC Base Repairs (B/W 7th and 14th St)

  • SD MH-7 (7th Street Intersection)


26 views0 comments