• Maryland Ave Community Information

Bi-Weekly Project Update for February 8-21, 2021



Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft SL/TS Poles (7th to 14th Street)

  • Work on bump-outs and straight curb (10th and 11th Street) (Outbound)

  • Work on Brick sidewalk (9th to 8th Street) (Outbound)

  • Miss Utility Tickets -Maryland Ave NE between 10th St and 14th St.

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic light foundations (8th to 14th St)

  • E. Pipe Stubs for street lights

  • SD I-40

  • SD M-38 (13th St intersection)

  • SD Basin Connecting Pipe M-7 to I-16 (7th Street)

  • Test Pits (B/w 10th and 14th St)

  • PCC Base Repairs (B/W 7th and 14th St)

  • SD MH-7 (7th Street Intersection)

To Week Look Ahead - Washington Gas and Light Ahead

  • 600 Block of Maryland Ave NE- Inbound Lane, Services Installation

  • 400 Block of C St NE - Inbound Lane, Services Installation

  • 300 Block of Mass. Ave Continue gas main installation

  • 1200/1300 Block of Maryland Ave continue disconnects.

Project Updates – DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft SL/TS Poles (7th to 14th Street)

  • Work on bump-outs and straight curb (10th and 11th Street) (Outbound)

  • Work on Brick sidewalk (9th to 8th Street) (Outbound)

  • Miss Utility Tickets -Maryland Ave NE between 10th St and 14th St.

  • Tree Protection (14th Street to 8th Street)

35 views0 comments