Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of curb and gutter, (9th and 8th Street)

  • Work on Bump-outs and Brick sidewalk (9th to 8th street)

  • Miss Utility Tickets -Maryland Ave NE between 10th St& 14th St

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 6th and 12th St)

  • Traffic light foundations (8th to 14th St)

  • Test Pits (B/w 10th and 14th St)

  • PCC Base Repairs (B/W 9th and 14th St)

  • SD MH-7 (7th street intersection).

  • Storm Drain Manhole 33 & 32 and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.

  • Storm Drain Manhole 4 installation on the MD Ave and 4th St intersection.

  • Storm Drain Inlet -13, and basin connection pipe installation on the MD Ave at D St.

  • Cast in place Storm Drain Manhole 7 on the MD Ave at 7th St intersection.


To Week Look Ahead - Washington Gas and Light Ahead

  • 600 Block of Maryland Ave NE, Inbound- Continue installation of the gas services.

  • 4th & Maryland Ave NE, and 7th & C St- Continue gas main installation.

  • 1200/1300 Block of Maryland Ave. - Continue disconnects.


Project Updates – DDOT

  • Continued transfer to temporary poles between 5th to 12th St.

  • Continued installation of 20Ft SL/TS Poles between 6th to 12th St.

  • Continued installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 8th St to 7th St.

  • Continued brick gutter, wheelchair ramps, granite curb, and brick sidewalk for the bump outs at inbound from 9th St.

  • Continued Storm Drain Inlet I-24 installation at 9th St intersection.

  • Continued PCC Base Repairs (B/W 9th and 14th St)