
Maryland Ave Community Information
Bi-Weekly Project Update for January 25, 2021- February 7, 2021
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Work on lead walks (8th and 10th Street)
Work on bump-outs and straight curb (10th and 11th Street) (Outbound)
Work on Brick sidewalk (9th to 8th Street) (Outbound)
Miss Utility Tickets -Maryland Ave NE between 1oth St and 14th St.
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 6th and 12th St)
Traffic light foundations (8th to 14th St)
E. Pipe Stubs for streetlights
E MH- 15.04
E MH-15.06
Test Pits (B/w 10th and 14th St)
PCC Base Repairs (B/W 9th and 14th St)
SD MH-7 (7th Street Intersection).
To Week Look Ahead - Washington Gas and Light Ahead
500 Block C St NE - Inbound, Continue installation of the gas service
4th & Maryland Ave NE, - 300 Block of Mass. Ave Continue gas main installation.
1200/1300 Block of Maryland Ave, continue disconnects.
Project Updates – DDOT
Transfer to temporary poles on between 5th to 12th St.
Continued installation of 20Ft SL/TS Poles between 6th to 12th St.
Continued installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 8th St to 7th St.
Continued brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at inbound from 9th St.
Continued Storm Drain Inlet I-24 installation at 9th St intersection.
Continued PCC Base Repairs (B/W 9th and 14th St)