• Maryland Ave Community Information

Bi-Weekly Project Update for 05/03/2021 – 05/16/2021

Two Week Look Ahead - DDOT

  • Transfer to temporary poles (7th to 14th Street)

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (4th to 14th street)

  • Work on Bio-retention (Elliot street) (outbound)

  • Work on Bump-outs (Elliot to 14th Street) (outbound)

  • Work on Brick sidewalk @7th to 6th street (Inbound)

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic/street light foundations (8th to 14th St)

  • PCC Base Repairs (B/W 8th and 14th St)

Two Week Look Ahead - Washington Gas and Light Ahead

  • 805 S St NE Services Installation

  • 4th and C St NE Continue disconnects.

  • D St and Maryland Ave, North side, continue disconnects.

  • 6th St and Maryland Ave, multiple locations continue disconnects.

  • 7th St and Maryland Ave, multiple locations continue disconnects

  • 8th St and Maryland Ave, multiple locations continue disconnects.

  • 9th St and Maryland Ave, multiple locations continue disconnects.

  • 10th St and Maryland Ave, multiple locations continue disconnects.

  • 700/800 Block of Maryland Ave continue disconnects.

Project Updates – DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (4th to 14th street)

  • Work on bump-outs and Bio-retention (Elliot and 13th street) (outbound)

  • Work on Brick Sidewalk (7th to 8th Street) (Outbound)

  • Work on sidewalk @7th to 6th street (Inbound)

  • Miss Utility Tickets -Maryland Ave between 14th St to 10th St

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic/street light foundations (8th to 14th St)

  • PCC Base Repairs (B/W 9th and 14th St