Bi-Weekly Project Update 06/28/2021 – 07/11/2021

Two Week Look Ahead - DDOT

  • Transfer to temporary poles (7th to 14th Street).

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (4th to 14th street)

  • Work on Medians (7th street to 6th street)

  • Topsoil on Medians (13th street,7th to 10th street)

  • Work on Brick sidewalk (12th Street intersection) (Outbound)

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 5th and 14th St)

  • Traffic/street light foundations (5th to 12th St)

  • PCC Base Repairs (B/W 6th and 12th St)


Two Week Look Ahead - Washington Gas and Light

  • 4th St & C St NE continue disconnects

  • 260 Maryland Ave, replace gas service


Project Updates – DDOT

  • Transfer to temporary poles between 7th to 14th Street.

  • Install 20ft & 28.5ft SL/TS poles between 7th to 14th Street.

  • Pulling cables for the communication &streetlights between 4th to 14th St.

  • Granite curb and brick sidewalk at 9th Street) (outbound)

  • Excavation, granite curb & median installation at Maryland Ave between 13th St & 14th St.

  • Miss Utility Tickets - Maryland Ave NE BTW 14th and 7th St.

  • Tree Protection (14th Street to 2nd Street)

  • Saw Cutting (B/W 7th and 14th St)

  • Traffic/street light foundations (8th to 14th St)

  • Traffic light foundations between 8th to 14th St.

  • PCC base repairs between 8th St and 14th St.

  • Remove and reinstall 18" RCP MH-32 to MH-33.

  • Topsoil on the median between 9th St to 10th St

  • Brick sidewalk installation at 8th Street intersection(outbound)

  • Inlet 34 installation at 11th St and MD Ave










28 views0 comments