Maryland Ave Community Information
Biweekly Progress Report 08/09/2021 – 08/22/2021
Two Week Look ahead by DDOT contractor
Transfer to temporary poles (11th Street)
Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)
Pulling Electric Cables for communication and streetlight (7th to 3rd street)
Pulling Fiber optic cables (7th to 3rd street)
Milling and Paving (15th street to 12th street)
Road Repairs (15th street to 12th street)
Work on Granite curb and sidewalk (3rd to 2nd street)
Brick sidewalk (3rd to 4th street) Outbound Subcontractor EURO
Miss Utility Tickets -14th & Maryland Ave NE to 2nd street)
Tree Protection (14th Street to 3rd Street)
Saw Cutting (B/W 6th and 2nd St)
Traffic/streetlight foundations (8th to 3rd St)
PCC Base Repairs (B/W 6th and 3rd St) As required
Clean storm Sewer inlets and manholes
Project Updates – DDOT
FMCC continued transfer to temporary poles between 7th ST to 14th St.
FMCC continued install 20ft & 28.5ft SL/TS poles between 7th St to 14th St.
FMCC cont. pulling cables for the communication &streetlights from 8th St to 3rd St.
FMCC continued excavation, granite curb and brick sidewalk at Maryland Ave between 2nd and 4th St.
Omni continued Traffic light foundations between 5th to 12th St.
Omni continued cleaning storm sewer manholes and inlets on Maryland Ave between 14th St to 4th St.