• Maryland Ave Community Information

Biweekly Progress Report 08/09/2021 – 08/22/2021

Two Week Look ahead by DDOT contractor

  • Transfer to temporary poles (11th Street)

  • Install 20Ft & 28.5 SL/TS Poles (7th to 14th St)

  • Pulling Electric Cables for communication and streetlight (7th to 3rd street)

  • Pulling Fiber optic cables (7th to 3rd street)

  • Milling and Paving (15th street to 12th street)

  • Road Repairs (15th street to 12th street)

  • Work on Granite curb and sidewalk (3rd to 2nd street)

  • Brick sidewalk (3rd to 4th street) Outbound Subcontractor EURO

  • Miss Utility Tickets -14th & Maryland Ave NE to 2nd street)

  • Tree Protection (14th Street to 3rd Street)

  • Saw Cutting (B/W 6th and 2nd St)

  • Traffic/streetlight foundations (8th to 3rd St)

  • PCC Base Repairs (B/W 6th and 3rd St) As required

  • Clean storm Sewer inlets and manholes


Project Updates – DDOT

  • FMCC continued transfer to temporary poles between 7th ST to 14th St.

  • FMCC continued install 20ft & 28.5ft SL/TS poles between 7th St to 14th St.

  • FMCC cont. pulling cables for the communication &streetlights from 8th St to 3rd St.

  • FMCC continued excavation, granite curb and brick sidewalk at Maryland Ave between 2nd and 4th St.

  • Omni continued Traffic light foundations between 5th to 12th St.

  • Omni continued cleaning storm sewer manholes and inlets on Maryland Ave between 14th St to 4th St.



46 views0 comments