
Maryland Ave Community Information
Biweekly Project Update 09/06/2021 – 09/19/2021
Two Week Look ahead by DDOT contractor
Pulling electric cables for communication and streetlight (10th to 3rd Street)
Pulling fiber optic cables (14th to 3rd street)
Work on granite curb and sidewalk (3rd to 2nd street) Outbound
Paving (11th to 8th street)
Work on medians (6th street to D street)
Pavement marking (14th street to 11th street)
PCC base repairs (B/W 10th and 3rd St) As required
Clean storm sewer inlets and manholes
Project Updates – DDOT
FMCC continued transfer to temporary poles between 7th St to 14th St.
FMCC continued install 20ft & 28.5ft SL/TS poles between 7th St to 14th St.
FMCC cont. pulling cables for the communication &streetlights from 10th St to 3rd St.
FMCC continued excavation, granite curb and brick sidewalk at Maryland Ave between 2nd and 4th St.
FMCC completed paving 11th to 15th street.
Omni continued Traffic light foundations between 5th to 12th St.
Omni continued cleaning storm sewer manholes and inlets on Maryland Ave between 14th St to 4th St.