Biweekly Project Update 09/20/2021 – 10/03/2021

Updated: Oct 18, 2021

Two Week Look ahead

  • Tree Protection (14th Street to 3rd Street)

  • Saw Cutting (B/W 6th and 2nd St) As required

  • Grounding test on electrical manholes

  • Pulling 4/0 cables (11th to 6th street)

  • Pulling 100pair communication cable (15th to 12th street)

  • Remove existing streetlight poles and energize the new poles (14th to 8th street)

  • Flexipave sidewalk installation at various locations

  • Work on Brick Sidewalk (3rd to 2nd street) EURO

  • Milling (6th to 4th street)- around the park

  • Paving (8th to 6th street)

  • Pavement Marking (8th street to 6th street) DC LINE

Project Updates – DDOT

  • FMCC continued transfer to temporary poles between 7th St to 14th St.

  • FMCC continued install 20ft & 28.5ft SL/TS poles between 7th St to 14th St.

  • FMCC continued pulling cables for the communication &streetlights from 15th St to 3rd St.

  • FMCC continued excavation, granite curb and brick sidewalk at Maryland Ave between 2nd and 4th St.

  • FMCC completed paving from 11th St to 6th Street.

  • DC Line continued thermoplastic pavement marking from 12th ST to 9th St

  • Omni continued Traffic light foundations between 5th to 12th St.