Two Week Look ahead by DDOT contractor

  • Tree Protection (14th Street to 3rd Street)

  • Saw Cutting (B/W 14th and 2nd St) As required

  • Grounding test on electrical manholes

  • Pulling 4/0 cables (4th to 3rd street)

  • Pulling 100pair communication cable (D street)

  • Remove existing streetlight poles and energize the new poles (8th to 3rd street)

  • Remove existing Foundations (8th to 3rd street)

  • Pavement Markings (4th/C NE Intersection & 14th,13th,11th & 8th intersections) Green paint for Bicycle Lane DC LINE

  • Landscaping (11th to 6th)