Project Update 09/23/19 - 09/29/19

Updated: Oct 18, 2019






Monday September 23- Sunday September 29, 2019

The following activities were completed this week: Transfer signal heads to newly installed mast arm at signal poles at Maryland Ave and 11th St intersection; transfer signal heads to newly installed mast arm at signal poles at Maryland Avenue and 12th St intersection; dug out test pit to recently conflict crossing at MH 28; performed excavation to furnish and install street light pole RL -15-07; install 20LF of 2 inch lateral at STA:62+78; installed rebars for footing for light pole; cast in place foundation for RL-15-07; install and backfill inlet I-44; install Main Line, 6-4" conduit between 11th St and 12th Street (MH 12.01, 12.02, and 11.01); install 1-2" conduit along Main Line leading to RL 12.01, 12.02, 12.03, and 12.04; backfill foundation for RL-15.07 and 20" lateral at STA62+78


*Please note: There was no construction on 09/23, 09/28, 09/29.