Project Update 08/03-08/09, 2020



Two Week Look Ahead


DDOT Project

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.

  • Brick Sidewalk on MD Ave and at 4th St & 5th St.

  • Work on Bump-outs, Ramps, and Medians on MD Ave and at 6th St & 5th St.

  • PCC Base repairs at 6th St, 4th St and Mass Ave intersections.

  • Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St and Mass Avenue intersection.

  • Electrical conduits for the street crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.

  • Storm Drain Manhole-09, Inlet-10 and basin connection pipe installation on the MD Ave at 7th St and D St intersection.

  • Storm Drain Manhole 33, Manhole 32 and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.

  • Storm Drain Inlet -23 &25, and basin connection pipe installation on the MD Ave at 9th St intersection.

  • Storm Drain Inlet -28 & 29, and basin connection pipe installation on the MD Ave at 10th St intersection.

  • Storm Drain Inlet -30 & 32, and basin connection pipe installation on the MD Ave at 11th St intersection.

Washington Gas/Light Project

  • WGL Crew 1 will continue working on the gas service replacement at 1300 & 1200 Block of Maryland Ave inbound.

  • WGL Crew 2 will continue working on the gas main installation on at 1100 Block of Maryland Ave inbound.


Project Progress 08/03-09/2020

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.

  • Installed brick Sidewalk on MD Ave and at 4th St & 5th St.

  • Work on Bump-outs, Ramps, and Medians on MD Ave and at 6th St & 5th St.

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.

  • Storm Drain Inlet -28 & basin connection pipe installation on the MD Ave at 10th St intersection.

  • PCC Base repairs at 6th St, 4th St and Mass Ave intersection

  • Storm Drain Inlet -29& basin connection pipe installation on the MD Ave at 10th St intersection