Maryland Ave Community Information
Project Update 08/17-08/23/20
DDOT Project - Two Week Look Ahead
Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.
Brick Sidewalk on MD Ave and at 6th St.
Work on Bump-outs, Ramps, and Medians at 6th St & C St.
PCC Base repairs at 4th St and Mass Ave intersections.
Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St and Mass Avenue intersection.
Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.
Storm Drain Manhole M 7 installation at 7th St intersection.
Washington Gas - Two Week Look Ahead
WGL Crew 1 will continue working on the gas service replacement at 1300 & 1200 Block of Maryland Ave inbound.
WGL Crew 2 will continue working on the Backfilling bell hole at 6th St & Maryland Ave & 7th St and D St pressure tie
Weekly Update
Continued installation of 20Ft SL/TS Poles and transfer the existing poles to the temporary base on Maryland Ave, outbound from 9th St to 4th St.
Continued bump‐outs and ramps installation at Maryland Ave and 6th St.
Continued brick sidewalk installation at Maryland Ave at 6th St intersection.
Continued electrical Street crossings and light pole foundations installation on Maryland Ave B/W 9th St and 12th St.
Continued SD Inlet-23 installation at Maryland Ave and 9th St intersection.
Installed storm drain inlet I-16 at Maryland Avenue and 7th St.
Continued bump‐outs and ramps installation at Maryland Ave and 6th St.
Continued brick sidewalk installation at Maryland Ave at 5th St intersection.
PCC base repair over the utility trenches at 4th St and Mass Ave intersection.