Project Update 08/17-08/23/20



DDOT Project - Two Week Look Ahead

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.

  • Brick Sidewalk on MD Ave and at 6th St.

  • Work on Bump-outs, Ramps, and Medians at 6th St & C St.

  • PCC Base repairs at 4th St and Mass Ave intersections.

  • Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St and Mass Avenue intersection.

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.

  • Storm Drain Manhole M 7 installation at 7th St intersection.

Washington Gas - Two Week Look Ahead

  • WGL Crew 1 will continue working on the gas service replacement at 1300 & 1200 Block of Maryland Ave inbound.

  • WGL Crew 2 will continue working on the Backfilling bell hole at 6th St & Maryland Ave & 7th St and D St pressure tie


Weekly Update

  • Continued installation of 20Ft SL/TS Poles and transfer the existing poles to the temporary base on Maryland Ave, outbound from 9th St to 4th St.

  • Continued bump‐outs and ramps installation at Maryland Ave and 6th St.

  • Continued brick sidewalk installation at Maryland Ave at 6th St intersection.

  • Continued electrical Street crossings and light pole foundations installation on Maryland Ave B/W 9th St and 12th St.

  • Continued SD Inlet-23 installation at Maryland Ave and 9th St intersection.

  • Installed storm drain inlet I-16 at Maryland Avenue and 7th St.

  • Continued bump‐outs and ramps installation at Maryland Ave and 6th St.

  • Continued brick sidewalk installation at Maryland Ave at 5th St intersection.

  • PCC base repair over the utility trenches at 4th St and Mass Ave intersection.