Two Week Look -DDOT Project

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 8th St.

  • Brick Sidewalk on MD at 7th St and D St and 6th St and Maryland Ave

  • Work on Bump-outs, Ramps, and Medians on MD Ave at 6th St and 7th St and D St.

  • Test pit over the water main for the fire hydrant installation on Maryland Ave between 4th & 5th St.

  • PCC Base repairs at 4th St and Mass Ave intersections and at Maryland Ave and D St.

  • Remove existing streetcar tracks at C St between 5th and 6th St.

  • Remove existing streetcar tracks at Maryland Ave between 7th and D St.

  • Electrical conduits and manholes installations for the Street Lights and Traffic signal at Maryland Ave at 6th St and 7th St

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 11th St to 12th St.

  • Storm Drain Manhole-09, Inlet-10 and basin connection pipe installation on the MD Ave at 7th St and D St intersection.

  • Storm Drain Manhole 33 & 32 and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.

  • Storm Drain Manhole 4 installation on the MD Ave and 4th St intersection.

  • Storm Drain Inlet -13, and basin connection pipe installation on the MD Ave at D St intersection.

  • Cast in place Storm Drain Manhole 7 on the MD Ave at 7th St intersection.

Two Week Look Ahead - Washington Gas

  • WGL Crew 1 will continue working on the gas service replacement at 1200 Block of Maryland Ave inbound.

  • WGL Crew 2 will continue working on the gas main installation on at 1100 Block of Maryland Ave inbound.

  • Fort Myer crew will work on the utility trench repairs at 1300 Block of Maryland Ave inbound

Project Progress 08/24 to 10/10

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 12th St.

  • Installed brick Sidewalk on MD Ave and at 3rd St, 4th St & C St, 5th Stand C St,

  • Work on Bump-outs, Ramps, and Medians on MD Ave and at7th St, 6th St & 5th St.

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 4th St to 12th St.

  • Storm Drain Inlet -28 & basin connection pipe installation on the MD Ave at 10th St intersection.

  • PCC Base repairs at 6th St, 5th, 4th St and Mass Ave intersection

  • Storm Drain Inlet Storm Drain Manhole M‐4 installation at 4th and C St

  • Storm Drain RCP pipe 15" I-31 to M-37 at11th street intersection

  • Storm Drain Inlet D I-31 installation at 11th street intersection

  • Storm Drain manhole MH-37 at 11th street intersection

  • Storm Drain RCP pipe 18" MH-37 to MH-16 at 11th street intersection

  • Removed I - 35 and install I-34 at 11th street intersection

  • Fire Hydrant installation at 4th St and C St intersection.

Lane Closures:

  • As a part of the Maryland Avenue NE Streetscape Project, DDOT and FMCC will continue daily lane closures on the outbound and inbound lanes at multiple locations on Maryland Ave NE between 2nd Street and 14th Street during summer and fall this year.

  • DDOT will maintain one lane each direction during daily lane closures

  • The daily lane closures for the DDOT work will be performed from 8:00am-5:00pm Monday – Friday and Saturdays as needed, weather and construction conditions permitting.