Project Update 09/09-15/2019



Construction work this week included:

  • The team continued installing the 2" and 6" electrical conduit along Maryland Ave NE between G and 13th St.

  • Continue to install electrical conduit and manholes on Maryland Avenue. Also begin storm drain excavation at Maryland and 14 Street