Project Update Nov 4-10, 2019




Construction for the Maryland Ave. NE Safety Project is moving smoothly. The team continues to install electrical conduits along the median between 11th & 8th Street and at 14th Street intersection as well installation of street light pole foundations. Tree protection fences were installed between 15th and 14th St. Continue working at Maryland Ave & 14th street and at Maryland Ave & 13th street NE


Please review the traffic advisory page for the most up to date information on lane closures.