• Maryland Ave Community Information

Project Update 10/04/2021 – 10/31/2021

Two Week Look ahead

  • Tree Protection (14th Street to 3rd Street)

  • Saw Cutting (B/W 14th and 2nd St) As required

  • Grounding test on electrical manholes

  • Pulling 4/0 cables (8th to 3rd street)

  • Pulling 100pair communication cable (14th to 3rd street)

  • Remove existing streetlight poles and energize the new poles (14th to 6th street)

  • Remove existing Foundations (14th to 2nd street)

  • Pavement Marking (6th street to 2nd street) DC LINE

  • Landscaping (13th to 6th) COOPER

  • Installing Signs (14th to 3rd street)


Project Updates – DDOT

  • FMCC continued energizing street light poles between 2nd St to 14th St.

  • FMCC continued working on signal heads and traffic signal control cabinets BTW 2nd St to 14th St.

  • FMCC cont. pulling cables for the communication &streetlights from 15th St to 3rd St.

  • FMCC completed paving from 6th St to 2nd street.

  • DC Line continued thermoplastic pavement marking from 8th to 2nd St Light








43 views2 comments