This update covers the project period November 25-Dec 1st. The team continued work along the Maryland Ave NE corridor that included:

· Electrical trench backfilling on Maryland Avenue NE from 14th St to 12th St intersections.

· Storm Sewer installation on Maryland Ave at 14th St intersection

· Removing trees and installing a temporary tree fence on the trees to remain on Maryland Avenue between 12th St and F St.

· Storm Sewer manhole installation on Maryland Ave at Elliott St intersection


*Bus Stop Relocation: There are no bus stop relocations to report at this time