12/21/2020 – 12/27/2020
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of curb and gutter, (10th and 9th Street)
Work on Bump-outs and Brick sidewalk (9th to 11th street)
Miss Utility Tickets – from 14th St to 10th & Maryland Ave NE
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 6th and 12th St)
Traffic light foundations (7th to 14th St)
Sd connect I-30 (11th St Intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
300 Block of Mass Ave NE, Gas main installation.
300 Block of 7th St NE- pre-clean up.
Project Updates – DDOT
Transfer to temporary poles on between 5th to 12th St.
Installation of 20Ft SL/TS Poles between 6th to 12th St.
Installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 10th St to 11th St.
Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at 11th St intersection.
SD FC-4 & M-15 installation at 11th St intersection.
Traffic light pole foundations between 7th to 14th St.