12/21/2020 – 12/27/2020



Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of curb and gutter, (10th and 9th Street)

  • Work on Bump-outs and Brick sidewalk (9th to 11th street)

  • Miss Utility Tickets – from 14th St to 10th & Maryland Ave NE

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 6th and 12th St)

  • Traffic light foundations (7th to 14th St)

  • Sd connect I-30 (11th St Intersection)

Two Week Look Ahead - Washington Gas and Light Ahead

  • 300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)

  • 300 Block of Mass Ave NE, Gas main installation.

  • 300 Block of 7th St NE- pre-clean up.

Project Updates – DDOT

  • Transfer to temporary poles on between 5th to 12th St.

  • Installation of 20Ft SL/TS Poles between 6th to 12th St.

  • Installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 10th St to 11th St.

  • Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at 11th St intersection.

  • SD FC-4 & M-15 installation at 11th St intersection.

  • Traffic light pole foundations between 7th to 14th St.