12/28/2020 – 01/03/2021
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of curb and gutter, (10th and 9th Street)
Work on Bump-outs and Brick sidewalk (9th to 11th street)
Miss Utility Tickets – from 14th St to 10th & Maryland Ave NE
Tree Protection (14th Street to 8th Street)
Traffic light foundations (7th to 14th St)
Sd connect I-57 (14th St Intersection)
PCC Base Repairs (B/W 11th and 14th st)
To Week Look Ahead - Washington Gas and Light Ahead
300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
300 Block of Mass Ave NE, Gas main installation.
Project Updates – DDOT
Transfer to temporary poles on between 6th to 12th St.
Installation of 20Ft SL/TS Poles between 6th to 12th St.
Installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 9th St to 10th St.
Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at inbound from 9th St to 10th St.
Storm Drain Inlet I-57 installation at 14th St intersection.
PCC Base Repairs on Maryland B/W 11th St and 14th St.