Project Update December 7-13, 2020
12/07/2020 – 12/13/2020
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of curb and gutter, (10th and 9th Street)
Work on Bump-outs and Brick sidewalk (9th to 11th street)
Miss Utility Tickets – from 14th St to 10th & Maryland Ave NE
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 6th and 12th St)
Streetlight foundations (7th to 14th St)
Test Pits (B/w 11 and 14th St)
E. MH-11.02 to MH-11.04 (11th St intersection)
E. MH-13.04 to MH-13.06 (13th St intersection)
Streetlight Foundations (B/w 12th and 13th)
PCC Base Repairs (B/W 11th and 14th St)
Sd connect I-30 (11th St Intersection)
SD FC-4 & M-15 (11th Street Intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
500/400 Block of Maryland Avenue NE - MAIN - INBOUND LANES
1300 Block disconnects- various locations: 13th St & Maryland Ave, G St & Maryland Ave, 13th St and F St NE
Project Updates – DDOT
Transfer to temporary poles on between 5th to 12th St.
Installation of 20Ft SL/TS Poles between 6th to 12th St.
Installation of curb and gutter and brick sidewalk installation at Maryland Ave, inbound from 14th and 13th St.
Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at F St and 10th St intersection.
Traffic light pole foundations between 7th to 14th St.
Electrical conduit and Manhole MH-11.02 to MH-11.04 and MH-11.04 to MH-11.01at 11th St intersection.
PCC Base Repairs on Maryland Ave outbound between 11th St & 14th St.
SD FC-6 installation between 12th to 13th St.