• Maryland Ave Community Information

Project Update December 7-13, 2020



12/07/2020 – 12/13/2020


Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of curb and gutter, (10th and 9th Street)

  • Work on Bump-outs and Brick sidewalk (9th to 11th street)

  • Miss Utility Tickets – from 14th St to 10th & Maryland Ave NE

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 6th and 12th St)

  • Streetlight foundations (7th to 14th St)

  • Test Pits (B/w 11 and 14th St)

  • E. MH-11.02 to MH-11.04 (11th St intersection)

  • E. MH-13.04 to MH-13.06 (13th St intersection)

  • Streetlight Foundations (B/w 12th and 13th)

  • PCC Base Repairs (B/W 11th and 14th St)

  • Sd connect I-30 (11th St Intersection)

  • SD FC-4 & M-15 (11th Street Intersection)


Two Week Look Ahead - Washington Gas and Light Ahead

  • 300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)

  • 500/400 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 1300 Block disconnects- various locations: 13th St & Maryland Ave, G St & Maryland Ave, 13th St and F St NE

Project Updates – DDOT

  • Transfer to temporary poles on between 5th to 12th St.

  • Installation of 20Ft SL/TS Poles between 6th to 12th St.

  • Installation of curb and gutter and brick sidewalk installation at Maryland Ave, inbound from 14th and 13th St.

  • Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at F St and 10th St intersection.

  • Traffic light pole foundations between 7th to 14th St.

  • Electrical conduit and Manhole MH-11.02 to MH-11.04 and MH-11.04 to MH-11.01at 11th St intersection.

  • PCC Base Repairs on Maryland Ave outbound between 11th St & 14th St.

  • SD FC-6 installation between 12th to 13th St.