The following are updates for the Maryland Ave NE Streetscape project for the week of February 24-March 1:

  • Electrical duct bank, installation on Maryland Avenue NE between 6th St and 5th St intersections.

  • 15” basin connect pipe installation between I47 and MH 26 @ Elliott St on Maryland Ave.

  • WGL continued 2” pressure gas main installation on Maryland Ave, Outbound, between 12th St to 13th Street

  • Installed Street Light poles along Maryland Ave, Inbound between 14th St &6th St.

***Please note: The bus stop location at Maryland Ave NE and 8th St NE has been temporarily closed while work is being performed at that intersection. Please use the next bus stop to board the bus.