Construction progress continues for the Maryland Ave NE Streetscape Project. This week it included:

  • The installation of an electrical duct bank, light pole foundation, and manhole installation at Maryland Ave NE between 10th and 6th street intersections.

  • Trench backfilling around new storm sewer MH26 at Maryland Ave OBL near Elliott St.


Some work was postponed this week due to rain.