
Maryland Ave Community Information
Project Update Jan. 27- Feb 2, 2020
The rehabilitation of Maryland Ave NE continued to progress this week and included the following:
Installed electrical duct bank, light pole foundation and manhole between 9th and 6th Street on Maryland Ave NE
Installed infrastructure to support new storm sewer
WGL continued sidewalk repair between 6th and 12th St
***Please note: The bus stop location at Maryland Ave NE and 8th St NE has been temporarily closed while work is being performed at that intersection. Please use the next bus stop to board the bus.
***Check the traffic advisory page for the latest traffic advisories
·