01/04/2021 – 01/10/2021





Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of curb and gutter, (8th and 7th Street)

  • Work on Bump-outs and Brick sidewalk (9th street)

  • Miss Utility Tickets -14th & Maryland Ave NE BTW 10th & Maryland Ave NE

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 6th and 12th St)

  • Traffic light foundations (8th to 14th St)

  • Test Pits (B/w 10 and 14th St)

  • PCC Base Repairs (B/W 9th and 14th St)

  • Sd connect I-27 (10th St Intersection)

  • Sd connect I-24 (9th St Intersection)

  • SD MH-7 (7th street intersection)

To Week Look Ahead - Washington Gas and Light Ahead

  • 600 Block of Maryland Avenue NE – SVCS (Inbound Lanes)

  • 300 Block of Mass Ave NE, Gas main installation.

  • 4th & Maryland Ave, Gas main installation.

Project Updates – DDOT

  • Installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 8th St to 7th St.

  • Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at inbound from 9th St.

  • Storm Drain Inlet I-27 installation at 10th St intersection.

  • PCC Base Repairs on Maryland B/W 9th St and 14th St.

  • Storm Drain Inlet I-24 installation at 9th St intersection.