Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of curb and gutter, (8th and 7th Street)
Work on Bump-outs and Brick sidewalk (9th street)
Miss Utility Tickets -14th & Maryland Ave NE BTW 10th & Maryland Ave NE
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 6th and 12th St)
Traffic light foundations (8th to 14th St)
Test Pits (B/w 10 and 14th St)
PCC Base Repairs (B/W 9th and 14th St)
Sd connect I-27 (10th St Intersection)
Sd connect I-24 (9th St Intersection)
SD MH-7 (7th street intersection)
To Week Look Ahead - Washington Gas and Light Ahead
600 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
300 Block of Mass Ave NE, Gas main installation.
4th & Maryland Ave, Gas main installation.
Project Updates – DDOT
Installation of curb, gutter and brick sidewalk installation at Maryland Ave, inbound from 8th St to 7th St.
Brick gutter, wheelchair ramps, granite curb and brick sidewalk for the bump outs at inbound from 9th St.
Storm Drain Inlet I-27 installation at 10th St intersection.
PCC Base Repairs on Maryland B/W 9th St and 14th St.
Storm Drain Inlet I-24 installation at 9th St intersection.