Construction activities this week included:

  • Electrical duct bank and electrical manhole installation on Maryland 5th and 4th St.

  • Installed concrete encasement of the 15” PCC Pipe between MH-2 to I-2 and MH-1 to I-1. Installed the riser section to basin I-2. Maryland Ave, between 2nd & 3rd St NE,

  • FMCC electrical crew continued installing #16 Cast Iron poles and transformer bases on Maryland Ave, inbound between 14th St and 6th St.

  • Backfilled the trenches for the 15” PCC Pipe between MH-2 to I-2 and MH-1 to I-1. Demolished the existing basin inlet EX/I-2. Started the sewer manhole MH-3 Installation on Maryland Ave, between 2nd & 3rd St NE.

  • Electrical duct bank and electrical manhole installation on Maryland 6th and 4th St.

  • Installed concrete storm sewer MH-3 on Maryland Ave, between 2nd & 3rd St NE

  • Electrical duct bank, street light pole foundations and electrical manhole installation on Maryland 6th and 4th St.

  • Storm drain RCP installation from M-2 to M-3 (B/W 2nd and 3rd St) on Maryland Avenue.