Project Update November 09-15, 2020



Two Week Look Ahead - DDOT Project


  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of Brick Sidewalk, work on bump-outs (11th and 12th St intersection)

  • Work on Bio retention (6th and Mass Ave)

  • Work on lead walks (12th to 13th Street) (Inbound)

  • Miss Utility Tickets -14th & Maryland Ave NE headed west toward 10th & Maryland Ave NE

  • Saw Cutting (B/W 6th and 12th St)

  • Streetlight foundations (6th to 12th St)

  • Test Pits (B/w 11 and 14th St)

  • SD M-43 (B/w Elliot and 13th St)

  • SD Basin connecting Pipe I-43 to M-23 (B/w Elliot and 13th St)

  • PCC Base Repairs (B/w Elliot and 13th St)

  • SD M-22

  • SD M-23 to M-22

  • SD FC-2 and M-12 (9th St intersection)

  • SD Basin connecting Pipe I-27 to M-14


Two Week Look Ahead - Washington Gas and Light Ahead


  • 600 Block of Maryland Avenue NE – SVCS (Inbound Lanes)

  • 700 Block of Maryland Avenue NE – SVCS (Inbound Lanes)

  • 600 Block of Maryland Avenue NE - MAIN - (Inbound Lanes)

  • 1300 Block of Maryland Avenue NE Disconnect, Various Locations, 13th & Maryland Avenue, Elliott St & Maryland Avenue, G St & Maryland Avenue NE


Project Updates - DDOT


  • Transfer to temporary poles (5th to 12th street)

  • Install of 20Ft SL/TS Poles (6th to 12th St)

  • Street light foundations (6th to 10th St)

  • Work on Bump outs (12th to 13th St) (Inbound)

  • Installation of Brick Sidewalk, work on bump outs and Bio‐retentions (11th and 12th St intersection)

  • Test Pits (B/W6th and 12th St)

  • SD Basin connecting Pipe I‐43 to M‐23 (B/w Elliot and 13th St)

  • PCC Base Repairs (B/w Elliot and 13th St)

  • SD M‐22 installation

  • SD M‐23 to M‐22 storm drainpipe installation

  • SD Basin connecting Pipe installation form I‐42 to M‐22

  • SD M‐14 installation

  • Storm drainpipe installation form SD FC‐2 and M‐12 (9th St intersection)

  • SD I‐51 installation (14th St intersection)

  • SD Basin connecting Pipe I‐27 to M‐14 installation


6 views0 comments