Project Update November 16-22, 2020
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of Brick Sidewalk, work on bump-outs (13th and 14th St intersection)
Work on Bio retention (6th and Mass Ave)
Work on lead walks (12th to 13th Street) (Inbound)
Saw Cutting (B/W 6th and 12th St)
Streetlight foundations (6th to 12th St)
Test Pits (B/w 11 and 14th St)
E. MH-11.02 to MH-11.04 (11th St intersection)
SD Basin connecting Pipe I-42 to M-22
SD FC-2 and M-12 (9th St intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
300 Block of Maryland Avenue NE – MAIN (Inbound Lanes)
600 Block of Maryland Avenue NE - MAIN - (Inbound Lanes)
1300 Block of Maryland Avenue NE Disconnect, Various Locations: 13th & Maryland Avenue, Elliott St & Maryland Avenue, G St & Maryland Avenue NE
Project Updates - DDOT
Transfer to temporary poles (5th to 12th street)
Install 20Ft SL/TS Poles (6th to 12th St)
Street light foundations (6th to 12th St)
Installation of Brick Sidewalk, work on bump outs and Bio‐retentions (6th St and Mass Ave)
Test Pits (B/W 11th and 14th St)
SD M‐23 to M‐22 storm drainpipe installation
SD Basin connecting Pipe installation form I‐42 to M‐22
SD Basin connecting Pipe I‐27 to M‐14 installation
SD Basin connecting Pipe SD FC-2 and M-12 (9th St intersection).