Project Update- November 2-8, 2020
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street)
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of Brick Sidewalk, work on bum-pouts and Bio-retentions (11th and 12th St intersection)
Work on lead walks (12th to 13th Street) (Inbound)
Saw Cutting (B/W 6th and 12th St)
Streetlight foundations (6th to 12th St)
Test Pits (B/w 11 and 14th St)
SD M-25 to M-23 (B/w Elliot and 13th St)
SD Basin connecting Pipe I-43 to M-23 (B/w Elliot and 13th St)
PCC Base Repairs (B/w Elliot and 13th St)
SD M-14
SD FC-2 and M-12 (9th St intersection)
SD I-53 (14th St intersection)
SD I-51 (14th St intersection)
SD Basin connecting Pipe I-27 to M-14
Two Week Look Ahead - Washington Gas and Light Ahead
700 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
900 Maryland Avenue NE – SVCS
902 Maryland Avenue NE – SVCS
904 Maryland Avenue NE – SVCS
600 Block of Maryland Avenue NE - MAIN - INBOUND LANES
1300 BLOCK DISCONNECTS - VARIOUS LOCATIONS: 13TH & MD, ELLIOT & MARYLAND, G ST & MD AVE
Project Updates - DDOT
Transfer to temporary poles (5th to 12th street)
Installation of 20Ft SL/TS Poles (6th to 12th St)
Street light foundations (6th to 10th St)
Work on Bump outs (12th to 13th St) (Inbound)
Test Pits (B/W11 and 13th St)
SD M-25 (B/W Elliot and 13th St)
SD M-25 to M-26 (B/w Elliot and 13th St)
SD M-23 (B/w Elliot and 13th St)
SD M-23 to M-16 (B/w Elliot and 13th St)
SD M-7 (7th street intersection).