Two Week Look Ahead - DDOT Project
• Transfer to temporary poles (5th to 12th street).
• Install 20Ft SL/TS Poles (6th to 12th St)
• Installation of Brick Sidewalk, work on bump-outs (13th and 14th St intersection)
• Work on Bio retention (6th and Mass Ave)
• Work on lead walks (12th to 13th Street) (Inbound)
• Saw Cutting (B/W 6th and 12th St)
• Streetlight foundations (6th to 12th St)
• Test Pits (B/w 11 and 14th St)
• E. MH-11.02 to MH-11.04 (11th St intersection)
• SD Basin connecting Pipe I-42 to M-22
• SD FC-2 and M-12 (9th St intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
• 300 Block of Maryland Avenue NE – MAIN (Inbound Lanes)
• 600 Block of Maryland Avenue NE - MAIN - (Inbound Lanes)
• 1300 Block of Maryland Avenue NE Disconnect, Various Locations, 13th & Maryland Avenue, Elliott St & Maryland Avenue, G St & Maryland Avenue NE
Project Updates – DDOT
• Transfer to temporary poles (5th to 12th street)
• Install 20Ft SL/TS Poles (6th to 12th St)
• Street light foundations (6th to 12th St)
• Installation of Brick Sidewalk, work on bump outs and Bio‐retentions (6th St and Mass Ave)
• Test Pits (B/W 11th and 14th St)
• SD M‐23 to M‐22 storm drainpipe installation
• SD Basin connecting Pipe installation form I‐42 to M‐22
• SD Basin connecting Pipe I‐27 to M‐14 installation
• SD Basin connecting Pipe SD FC-2 and M-12 (9th St intersection).