• Maryland Ave Community Information

Project Update November 23-29, 2020

Updated: Dec 11, 2020



Two Week Look Ahead - DDOT Project


• Transfer to temporary poles (5th to 12th street).

• Install 20Ft SL/TS Poles (6th to 12th St)

• Installation of Brick Sidewalk, work on bump-outs (13th and 14th St intersection)

• Work on Bio retention (6th and Mass Ave)

• Work on lead walks (12th to 13th Street) (Inbound)

• Saw Cutting (B/W 6th and 12th St)

• Streetlight foundations (6th to 12th St)

• Test Pits (B/w 11 and 14th St)

• E. MH-11.02 to MH-11.04 (11th St intersection)

• SD Basin connecting Pipe I-42 to M-22

• SD FC-2 and M-12 (9th St intersection)


Two Week Look Ahead - Washington Gas and Light Ahead


• 300 Block of Maryland Avenue NE – MAIN (Inbound Lanes)

• 600 Block of Maryland Avenue NE - MAIN - (Inbound Lanes)

• 1300 Block of Maryland Avenue NE Disconnect, Various Locations, 13th & Maryland Avenue, Elliott St & Maryland Avenue, G St & Maryland Avenue NE


Project Updates – DDOT


• Transfer to temporary poles (5th to 12th street)

• Install 20Ft SL/TS Poles (6th to 12th St)

• Street light foundations (6th to 12th St)

• Installation of Brick Sidewalk, work on bump outs and Bio‐retentions (6th St and Mass Ave)

• Test Pits (B/W 11th and 14th St)

• SD M‐23 to M‐22 storm drainpipe installation

• SD Basin connecting Pipe installation form I‐42 to M‐22

• SD Basin connecting Pipe I‐27 to M‐14 installation

• SD Basin connecting Pipe SD FC-2 and M-12 (9th St intersection).


Recent Posts

See All

© 2019 All Rights Reserved. Page managed by Nspiregreen LLC