11/30/2020 – 12/06/2020
Two Week Look Ahead - DDOT Project
Transfer to temporary poles (5th to 12th street).
Install 20Ft SL/TS Poles (6th to 12th St)
Installation of curb and gutter, repair sidewalk (14th and 13th St intersection)
Work on Bump-out and Brick sidewalk (F and 10th St Intersection)
Miss Utility Tickets (Maryland Ave NE from 14th St to10th St)
Tree Protection (14th Street to 8th Street)
Saw Cutting (B/W 6th and 12th St)
Streetlight foundations (7th to 14th St)
Test Pits (B/w 11 and 14th St)
E. MH-13.08 to MH-13.04 (13th St Intersection)
PCC Base Repairs (B/W 11th and 14th St)
Sd connect I-40 (13th St Intersection)
SD FC-6 and M-35 (B/W 12th St and 13th St)
Sd connect I-27 (10th St Intersection)
Two Week Look Ahead - Washington Gas and Light Ahead
300 Block of Maryland Avenue NE – SVCS (Inbound Lanes)
500/400 Block of Maryland Avenue NE - MAIN - INBOUND LANES
1300 Block disconnects- various locations: 13th St & Maryland Ave, G St & Maryland Ave, 13th St and F St NE
Project Updates – DDOT
Transfer to temporary poles on between 5th to 12th St.
Install 20Ft SL/TS Poles between 6th to 12th St.
Bioretention installation at 6th and Mass Ave, 7th St and D St.
Installation of Brick Sidewalk, curb, gutter, and wheelchair on Maryland Ave inbound from 13th St to 12th St.
Installation of curb and gutter on Maryland Ave, inbound between 14th and 13th St.
Street light foundations from 12th to 13th St.
Traffic light pole foundations between 12th to 13th St.
Test Pits B/W 11th and 14th St.
Electrical conduit and Manhole MH-11.02 to MH-11.04 & MH-11.02 installation at 11th St.
Electrical conduit and Manhole MH-13.08 to MH-13.04 (13th St intersection
SD FC-6 installation between 12th to 13th St.
Sd connect I-43