Project Update October 12-18




Two Week Look Ahead - DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS Poles (6th to 12th St)

  • Installation of Brick Sidewalk, work on bump-outs and Bio-retentions (6th St & Mass Ave)

  • Work on Traffic Islands and medians (4th & C St)

  • Miss Utility Tickets -14th & Maryland Ave NE headed west toward 10th & Maryland Ave NE

  • Tree Protection (14th Street to 8th Street)

  • Saw Cutting (B/W 6th and 12th St)

  • Streetlight foundations (6th to 10th St)

  • SD RCP Pipe M-10 to M-9A to M-9 (7th St & D St)

  • SD Basin connecting Pipe I-20 to M-10 (7th St & D St)

  • SD FC-5 and M-19 (B/W 11th and 12th St)

  • SD Basin connecting Pipe I-35 to M-9

  • Test Pits (B/w Elliot and 13th St)

  • SD M-25 (B/w Elliot and 13th St)

  • SD M-25 to M-26 (B/w Elliot and 13th St)

Two Week Look Ahead - Washington Gas and Light Ahead

  • 700 Block of Maryland Avenue NE - SVCS

  • 1000 Block of Maryland Avenue NE – SVCS

  • 700 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 1000 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 1000 Block of Maryland Avenue NE - MAIN -TIE IN @ 9TH ST NE

  • 1300 BLOCK DISCONNECTS

Project Updates - DDOT

  • Continued transfer existing poles to temporary poles and installation of 20Ft SL/TS Poles from 6th St to 12th St on Maryland Ave.

  • Continued Brick Sidewalk and bump outs installation at 7th St and Maryland Ave.

  • Continued Brick Sidewalk, bioretention and bump outs installation at 6th St and Mass Ave.

  • Continued working on Bump-outs and Ramps and medians at 4th St and C St.

  • Continued Street light foundations from 5th St to 10th St on Maryland Ave.

  • Continued SD FC‐5 and M‐19 B/W 11th and 12th St on Maryland Ave.

  • Omni continued Storm Drain Brick MH M-19 at 12th St and Maryland Ave.