Project Update October 19-25, 2020



Two Week Look Ahead - DDOT Project

  • · Transfer to temporary poles (5th to 12th street).

  • · Install 20Ft SL/TS Poles (6th to 12th St)

  • · Installation of Brick Sidewalk, work on bump-outs and Bio-retentions (6th St & Mass Ave and 7th and D St)

  • · Work on Bump-outs (12th to 13th street) (Inbound)

  • · Miss Utility Tickets -14th & Maryland Ave NE headed west toward 10th & Maryland Ave NE

  • · Saw Cutting (B/W 6th and 12th St)

  • · Streetlight foundations (6th to 10th St)

  • · SD Basin connecting Pipe M-37 to Ex. M-10 (11th St intersection)

  • · SD Basin connecting Pipe I-32 to Ex. M-10 (11th St intersection)

  • · SD Basin connecting Pipe I-35 to M-9

  • · SD Basin connecting Pipe I-36 to M-9

  • · Test Pits (B/w 11 and 13th St)

  • · SD I-40 (13th street intersection)

  • · SD M-25 (B/w Elliot and 13th St)

  • · SD M-25 to M-26 (B/w Elliot and 13th St)

  • · SD M-7 (7th street intersection)

Washington Gas and Light

  • 700 Block of Maryland Avenue NE - SVCS

  • 600 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 700 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 1300 BLOCK DISCONNECTS

DDOT Project Update

  • Continued transfer existing poles to temporary poles and installation of 20Ft SL/TS Poles from 6th St to 12th St on Maryland Ave.

  • Continued Brick Sidewalk and bump outs installation at 7th St and Maryland Ave.

  • Continued Brick Sidewalk, bioretention and bump outs installation at 6th St and Mass Ave.

  • Continued working on Bump-outs and Ramps and medians at 4th St and C St.

  • Continued Street light foundations from 6th St to 10th St on Maryland Ave.

  • Continued SD FC‐5 and M‐19 installation B/W 11th and 12th St on Maryland Ave.

  • Continued RCP pipe installation from SD M-25 to M-26 B/W Elliot and 13th St.

  • Continued SD Basin connecting Pipe I-20 to M-10 at 7th St & D St.