Project Update October 19-25, 2020
Two Week Look Ahead - DDOT Project
· Transfer to temporary poles (5th to 12th street).
· Install 20Ft SL/TS Poles (6th to 12th St)
· Installation of Brick Sidewalk, work on bump-outs and Bio-retentions (6th St & Mass Ave and 7th and D St)
· Work on Bump-outs (12th to 13th street) (Inbound)
· Miss Utility Tickets -14th & Maryland Ave NE headed west toward 10th & Maryland Ave NE
· Saw Cutting (B/W 6th and 12th St)
· Streetlight foundations (6th to 10th St)
· SD Basin connecting Pipe M-37 to Ex. M-10 (11th St intersection)
· SD Basin connecting Pipe I-32 to Ex. M-10 (11th St intersection)
· SD Basin connecting Pipe I-35 to M-9
· SD Basin connecting Pipe I-36 to M-9
· Test Pits (B/w 11 and 13th St)
· SD I-40 (13th street intersection)
· SD M-25 (B/w Elliot and 13th St)
· SD M-25 to M-26 (B/w Elliot and 13th St)
· SD M-7 (7th street intersection)
Washington Gas and Light
700 Block of Maryland Avenue NE - SVCS
600 Block of Maryland Avenue NE - MAIN - INBOUND LANES
700 Block of Maryland Avenue NE - MAIN - INBOUND LANES
1300 BLOCK DISCONNECTS
DDOT Project Update
Continued transfer existing poles to temporary poles and installation of 20Ft SL/TS Poles from 6th St to 12th St on Maryland Ave.
Continued Brick Sidewalk and bump outs installation at 7th St and Maryland Ave.
Continued Brick Sidewalk, bioretention and bump outs installation at 6th St and Mass Ave.
Continued working on Bump-outs and Ramps and medians at 4th St and C St.
Continued Street light foundations from 6th St to 10th St on Maryland Ave.
Continued SD FC‐5 and M‐19 installation B/W 11th and 12th St on Maryland Ave.
Continued RCP pipe installation from SD M-25 to M-26 B/W Elliot and 13th St.
Continued SD Basin connecting Pipe I-20 to M-10 at 7th St & D St.