Two Week Look Ahead DDOT Project

  • Transfer to temporary poles (5th to 12th street).

  • Install 20Ft SL/TS (stop light and traffic signal) Poles (6th to 12th St)

  • Brick Sidewalk, bump-outs and Bio-retentions installation (6th St & Mass Ave)

  • Work on Traffic Islands and medians (4th & C St)

  • Saw Cutting (B/W 6th and 12th St)

  • Streetlight foundations (5th to 10th St)

  • E. MH 12.07 stub MH-12.05 (B/W 11th and 12th St)

  • Storm Drain MH M-9A installation at (7th St & D St)

  • Storm Drain RCP Pipe installation from MH M-10 to M-9A to M-9 at (7th St & D St)

  • Storm Drain FC-5 and HM M-19 installation at (B/W 11th and 12th St)

  • Test Pits at (B/w Elliot and 13th St)

  • Storm Drain MH M-25 to M-26 installation at (B/w Elliot and 13th St)

Two Week Look Ahead Washington Gas & Light

  • Trench repairs at 1300 block of Maryland Ave NE (inbound lanes)

  • 1200 Block of Maryland Avenue NE - SVCS

  • 1100 Block of Maryland Avenue NE – SVCS

  • 1100 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 1000 Block of Maryland Avenue NE - MAIN - INBOUND LANES

  • 800 Block of Maryland Avenue NE - MAIN - INBOUND LANES

DDOT Project Progress October 5-10

  • Continued transfer existing poles to temporary poles and installation of 20Ft SL/TS Poles from 6th St to 12th St on Maryland Ave.

  • Continued Brick Sidewalk and bump outs installation at 7th St and Maryland Ave

  • Working on Bump-outs and Ramps and medians at 4th St and C St.

  • Continued Street light foundations from 4th St to 8th St on Maryland Ave.

  • Continued E. street crossings between 11th St and 12th St

  • Installed fire hydrants at 4th and C St

  • Performed PCC Base Repairs at 11th and Maryland Ave (outbound)

  • Continued Cast-in Place Storm Drain MH M-7 at 7th St and Maryland Ave.

  • Continued Storm Drain RCP Pipe M-10 to M-9A to M-9 at 7th St & D St.