- Maryland Ave Community Information
Project Updates 05/18-24/2020
Updated: Jun 17, 2020
DDOT Project Team contractor Fort Myer Construction
Maryland Avenue NE, Inbound between 14th St to 7th St, PCC base repairs, temporary asphalt placement, street light poles, PCC bus pads, and temporary pavement marking installation.
Maryland Avenue NE, Outbound between 4th St and 6th St, installed storm drains, inlets, and storm drain manholes
Maryland Avenue NE, between 2nd St and 4th St, electric duct banks, conduits, electrical manholes, and street light pole foundations installations.
Maryland Avenue NE, Inbound between 7th St to 6th PCC base repairs over the utility trenches.
Washington Gas contractor Infrasource
All main abandonment, installation & service replacement work along the outbound lanes of Maryland Avenue (3rd -6th Street NE). This includes work on the south side of C Street and work on the 600th Block of Massachusetts Ave. NE.
All main installation and service replacement work on Maryland Avenue between 6th Street NE and 13th Street NE.
Main installation work has been completed at the following locations:
C St & 7th St NE, 8th St & Maryland Ave NE, 9th and D St NE & Intersections of 11th St & Maryland Ave NE
Work at the intersection of E ST & 9th St NE (northeast corner of intersection) has been completed.