Two Week Look Ahead
DDOT
Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 8th St.
Work on Bump-outs, Brick Sidewalk, Ramps, and Medians on MD Ave and at 4th St & 5th St.
Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St and Mass Avenue intersection.
Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 9th St.
Storm Drain Inlet -30 & 32, and basin connection pipe installation on the MD Ave at 11th St intersection.
Storm Drain Inlet -28&29, and basin connection pipe installation on the MD Ave at 10th St intersection.
Storm Drain Manhole-09, Inlet-10 and basin connection pipe installation on the MD Ave at 7th St and D St intersection.
Storm Drain Inlet -23 and basin connection pipe installation on the MD Ave at 9th St intersection.
Storm Drain Manhole 33, Manhole 32 and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.
Washington Gas and Light
·WGL Crew 1 will continue working on the gas service replacement at 1300 Block of Maryland Ave inbound.
WGL Crew 2 will continue working on the gas main installation on at 1200 Block of Maryland Ave inbound
Project Progress 07/27-08/02, 2020
· FMCC continued installation of 20Ft SL/TS Poles on Maryland Ave, OBL from 4th St to 8th St.
· FMCC continued bump‐outs, median island, and ramps installation at Maryland Ave at 4th St and 5th St.
· FMCC bump-outs, brick sidewalk, ramps, and medians installation on Maryland Ave outbound at 4th St and 5th St intersection.
· Electrical conduits and manholes installations for the Street Lights and Traffic signal at 6th St and Mass Avenue intersection.
· Electrical conduits for the street crossings and light pole foundations installation on MD Ave outbound between 7th St to 9th St.
· Storm Drain Manhole-09, Inlet-10 and basin connection pipe installation on the MD Ave at 7th St and D St intersection
· Storm Drain Inlet -28&29, and basin connection pipe installation on the MD Ave at 10th St intersection.
· Electrical conduits and manholes installations for the street lights and traffic signal at Stanton Park.
· Storm Drain Inlet -23 and basin connection pipe installation on the MD Ave at 9th St intersection.
· Storm Drain Manhole 33, Manhole 32 and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.