• Maryland Ave Community Information

Project Updates 08/10-16/20



DDOT - Two Week Look Ahead

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.

  • Brick Sidewalk on MD Ave and at 4th St & 5th St.

  • Work on Bump-outs, Ramps, and Medians on MD Ave and at 6th St & 5th St.

  • PCC Base repairs at 6th St, 4th St, and Mass Ave intersections.

  • Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St, and Mass Avenue intersection.

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.

  • Storm Drain Manhole-09, Inlet-10, and basin connection pipe installation on the MD Ave at 7th St and D St intersection.

  • Storm Drain Manhole 33, Manhole 32, and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.

  • Storm Drain Inlet -23 &25, and basin connection pipe installation on the MD Ave at 9th St intersection.

  • Storm Drain Inlet -28 & 29, and basin connection pipe installation on the MD Ave at 10th St intersection.

  • Storm Drain Inlet -30 & 32, and basin connection pipe installation on the MD Ave at 11th St intersection.


Washington Gas - Two Week Look Ahead

  • WGL Crew 1 will continue working on the gas service replacement at 1300 & 1200 Block of Maryland Ave inbound.

  • WGL Crew 2 will continue working on the gas main installation on at 1100 Block of Maryland Ave inbound.


Weekly Progress Report


  • Team continued the installation of 20Ft SL/TS Poles and transfer the existing poles to the temporary base on Maryland Ave, outbound from 9th St to 4th St.

  • Team continued bump‐outs and ramps installation at Maryland Ave and 6th St.

  • Team continued brick sidewalk installation at Maryland Ave at 6th St intersection.

  • Team continued PCC base repair over the utility trenches at 4th St and Mass Ave intersection.

  • Team continued electrical Street Crossings and light pole foundations installation on Maryland Ave B/W 9th St and 12th St.

  • Team continued SD Inlet-23 installation at Maryland Ave and 9th St intersection.

  • Team continued SD Inlet-28 installation at Maryland Ave and 10th St intersection.

  • Team continued S.D. RCP pipe installation from MH-33 to MH-32 at Maryland Ave B/W 6th and 7th St intersection.

  • Team continued SD Inlet-30 & 32 installation at Maryland Ave and 11th St intersection.


© 2019 All Rights Reserved. Page managed by Nspiregreen LLC