Project Updates 08/10-16/20
DDOT - Two Week Look Ahead
Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 9th St.
Brick Sidewalk on MD Ave and at 4th St & 5th St.
Work on Bump-outs, Ramps, and Medians on MD Ave and at 6th St & 5th St.
PCC Base repairs at 6th St, 4th St, and Mass Ave intersections.
Electrical conduits and manholes installations for the Street Lights and Traffic signal at Stanton Park, 6th St, and Mass Avenue intersection.
Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 10th St.
Storm Drain Manhole-09, Inlet-10, and basin connection pipe installation on the MD Ave at 7th St and D St intersection.
Storm Drain Manhole 33, Manhole 32, and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.
Storm Drain Inlet -23 &25, and basin connection pipe installation on the MD Ave at 9th St intersection.
Storm Drain Inlet -28 & 29, and basin connection pipe installation on the MD Ave at 10th St intersection.
Storm Drain Inlet -30 & 32, and basin connection pipe installation on the MD Ave at 11th St intersection.
Washington Gas - Two Week Look Ahead
WGL Crew 1 will continue working on the gas service replacement at 1300 & 1200 Block of Maryland Ave inbound.
WGL Crew 2 will continue working on the gas main installation on at 1100 Block of Maryland Ave inbound.
Weekly Progress Report
Team continued the installation of 20Ft SL/TS Poles and transfer the existing poles to the temporary base on Maryland Ave, outbound from 9th St to 4th St.
Team continued bump‐outs and ramps installation at Maryland Ave and 6th St.
Team continued brick sidewalk installation at Maryland Ave at 6th St intersection.
Team continued PCC base repair over the utility trenches at 4th St and Mass Ave intersection.
Team continued electrical Street Crossings and light pole foundations installation on Maryland Ave B/W 9th St and 12th St.
Team continued SD Inlet-23 installation at Maryland Ave and 9th St intersection.
Team continued SD Inlet-28 installation at Maryland Ave and 10th St intersection.
Team continued S.D. RCP pipe installation from MH-33 to MH-32 at Maryland Ave B/W 6th and 7th St intersection.
Team continued SD Inlet-30 & 32 installation at Maryland Ave and 11th St intersection.