The two week look ahead is now included as a part of the project update. The updates, which included work performed for the DDOT project, are listed after the two week look ahead.


DDOT Two Week Look Ahead

  • Transfer to temporary light poles and install new poles 20Ft SL/TS Poles on Maryland Ave 4th St to 8th St. 

  • Work on bump-outs, brick sidewalk, ramps, and medians on MD Ave and at 4th St &  5th St.

  • Electrical conduits and manholes installations for the street lights and traffic signal at Stanton Park, 6th St and Mass Avenue intersection. 

  • Electrical conduits for the Street Crossings and light pole foundations installation on MD Ave outbound between 7th St to 9th St.

  • Storm Drain Inlet -28, and basin connection pipe installation on the MD Ave at 10th St intersection. 

  • Storm Drain Manhole-09, Inlet-10 and basin connection pipe installation on the MD Ave at 7th St and D St intersection. 

  • Storm Drain Manhole 33, Manhole 34, and RCP storm drainpipe installation on the MD Ave between 6th St and 7th St intersection.

Washington Gas Two Week Look Ahead

  • WGL Crew 1 will continue working on the gas service replacement at 1300 Block of Maryland Ave inbound.

  • WGL Crew 2 will continue working on the gas main installation on at 1200 Block of Maryland Ave inbound.


Weekly Update July 20-26, 2020


  • Continued installation of 20Ft SL/TS Poles on Maryland Ave, outbound from 4th  St to 8th St.

  • Continued bump‐outs, median island, and ramps installation at Maryland Ave at 4th St and 5th St. 

  • Continued brick sidewalk installation at Maryland Ave outbound at 4th St and 5th St intersection. 

  • Continued electrical conduit installation from MH-3.13 to MH-3.08 at Mass Ave and 6th St. 

  • Continued electrical Street Crossings and light pole foundations installation at Maryland Ave, Outbound between 6th St to 9th St intersections.

  • Team continued sewer manhole M-33 to M-32 on Maryland Ave between 6th St and 7th St. 

  • Continued SD Manhole- SD M-9 installation at Maryland Ave at D St and 7th St intersection.