• Maryland Ave Community Information

Project Updates April 13-19, 2020



The Maryland Ave NE Streetscape team continues to make safety improvements along the corridor. This weeks progress included:

  • Electrical duct bank and electrical manhole installation on Maryland Ave along the WB of C str and 4th str intersection towards 5th St. Installed 4-4” in PVC conduits towards MH 4.09 and installed 1-2” and 1-4” PVC conduits towards Pendant post streetlight pole foundation TS-3 and installed 1-2” PVC conduits on half crossing of C str. (WBL) towards the pole foundation RL 4.01.

  • Excavated and installed of sewer manholes MH-29 and MH-30 along Maryland Avenue between 3rd and 4th Street NE.

  • Electrical manhole MH 4.05 installation on Maryland Ave at SW corner of the 4th st and the EB of the Massachusetts Avenue NE intersection. Excavated light pole foundation trench and installed footing rebar and form work for the traffic signal pole foundations TS-6. Installed 1-2” and 1-4” PVC conduits from TS-6 to proposed manhole MH-4.05.

  • Electrical duct bank installation at MH-1.08 to MH-1.09. Excavated and installed two electrical manholes MH-1.09 and MH-1.08. All electrical trench from the previous workday was backfilled and temporary asphalt was placed as needed.

  • Continued installation of the 18” PCC pipe between sewer manhole MH-29 and MH-30. Completed the installation of sewer manhole MH-29.

  • Electrical duct bank installation on Maryland along the WB of C St ,4th St intersection towards 5th St. Installed 4-4” in PVC conduits towards MH 4.09 and installed 1-2” and 1-4” PVC conduits towards Pendant post streetlight pole foundation TS-3 and installed 1-2” PVC conduits on half crossing of C St (WBL) towards the pole foundation RL 4.01.

  • Electrical duct bank installation on Maryland between 1st and 2nd St form electrical MH-1.04 TWD MH-1.09 and CP/1.05/ to MH-1.04. Excavated and installed electrical manhole MH-1.04. All electrical trench from the previous workday was backfilled and temporary asphalt was placed as needed.

  • Started the installation of the 18” PCC pipe between sewer manhole MH-31 and MH-30. Completed the backfill around sewer manhole MH-30 and installed sewer manhole MH-31.

  • FMCC resumed PCC Base installation in existing median between 13th and 14th Street along Maryland Avenue.

  • Fort Myer setup lane closures on WBL and EBL of MD Avenue NE between the 14th St and 13th St intersections. Demolished existing median, excavated subbase, placed base course and PCC base from sta. 58+16 to sta.51+15.