Project Updates: April 20-26, 2020




Updates for the Maryland Ave NE Safety Rehabilitation Project include:

  • Lane closures on the west-bound and east-bound lanes of Maryland Ave NE between 11th St and 13th St to demolish existing median and excavate sub-base

  • Contractor placed hot mix temporary asphalt in median from sta.51+25 to .58+50

  • Excavated the trenches for the electrical duct bank installations from MH-1.09 to SL- 1.02, MH-1.09 TWD TS-9/ at 3rd St, MH-4.01 TWD TS-5 at 4th St., MH-4.01 TWD P.FEED/Stub, MH-1.08 to MH-1.07, and MH-1.04/Stub to MH-1.09 at 2nd St.

  • Excavated and installed electrical manhole MH-1.07. Electrical trench was backfilled and temporary asphalt

  • continued the installation of the 18” PCC pipe between sewer manhole MH-31 and MH-30. Completed the backfill around sewer manhole MH-31 along Maryland Avenue between 3rd and 4th Street NE

  • continued backfilling the electrical trenches along Maryland Avenue between 4th and 2nd Street NE.. Excavated three streetlight pole foundations and completed the installation of the 1-2” conduit to pole foundation RL-1.02.

  • Excavated and installed catch basin inlet I-8 and test pit in two locations for the installation of the 18” PCC pipe between manholes MH-31 and MH-36 along Maryland Avenue between 3rd and 4th Street NE.

  • Installed temporary tree protections within Stanton Park Circle.

  • Completed the excavation and installation of two catch basin inlet: inlets I-5 and I-7. Performed test pit at one location for the installation of the 18” PCC pipe between manholes MH-31 and MH-36 along Maryland Avenue between 3rd and 4th Street NE

  • Fort Myer setup lane closures on WBL and EBL of MD Avenue NE between the 11th St and 12th St intersections Demolished existing median, excavated subbase, placed base course and PCC base from sta. 42+75 to sta.48+98.

  • Setup lane closures on WBL of MD Avenue NE between the 14th St and G St intersections. Started repairing utility cut repairs by placing PCC base over the utility trenches

  • Fort Myer setup lane closures on WBL and EBL of MD Avenue NE between the 10th St and 11th St intersections. Demolished existing median, excavated subbase, placed base course and PCC base from sta. 39+00 to sta.40+80.

  • Excavated trenches for the electrical duct bank and streetlight pole foundations installation along Maryland Avenue between 2nd and 3rd Street NE.

  • Continued installation of the 18” PCC pipe between manholes for the inlets I-5 and I- 7 between manholes MH-31 and MH-36 along Maryland Avenue between 3rd and 4th Street NE.

  • Setup lane closures on WBL of MD Avenue NE between the 13th St and G St intersections. Continued repairing utility cut repairs by placing PCC base over the utility trenches.

  • Setup lane closures on WBL and EBL of MD Avenue NE between the 10th St and 11th St intersections. Demolished existing median, excavated subbase, placed base course and PCC base.

  • Continued installation of the storm sewer inlets I-6 along Maryland Avenue between 3rd and 4th Street NE.