Project Updates: April 27-May 3, 2020



Progress on the Maryland Ave NE Streetscape project continues. This weeks progress included:


  • Installation of 62.71 Tons of 2” temporary 12.5mm HMA surface course asphalt on PCC base trenches between the approximate stations 37+32 - 43+00 and along the crossings between13th street and 14th street towards the pole foundations.

  • Setup lane closures on WBL and EBL of MD Avenue NE between the 14th St and 9th St intersections, demolished existing median and utility trenches excavated subbase, placed base course and PCC base.

  • Excavated and installed 15” RCP basin connect pipe between MH-30 and I-6 between 3rd and 4th Street NE.

  • Electrical crew continued installing T bases, #16 Cast Iron Pole, 28.5-foot Pendant Pole, and 20-foot Traffic Signal Poles on Maryland Avenue, inbound between 14th St and 6th St.

  • Setup lane closures on WBL of MD Avenue NE between the 14th St and 13th St intersections, removed temporary asphalt from utility trenches, excavated subbase, placed base course and PCC base for the utility cut repairs.

  • Continued excavation and installation of 15” RCP basin connect pipe between sewer MH-30 and Inlet I-6 and between existing sewer EX MH -3 to I-8 on Maryland Avenue 3rd and 5th Street NE.

  • Setup lane closures on WBL of MD Avenue NE between the 14th St and 11th St intersections, continued utility trench repairs between the 11th St and the 12th St intersections on the lateral trenches between Manholes MH-11.01 and MH-11.05 , crossings the WBL from the median towards the pole foundations : RL 11.03, RL 12.01,RL 12.03, and at the 14th St and between the Manholes : MH-15.05 and MH-15.07.

  • Continued excavation and installation of 15” RCP basin connect pipe between sewer MH-30 and Inlet I-6 and between existing sewer EX MH -3 to I-8 on Maryland Avenue 3rd and 5th Street NE.

  • Electrical crew continued T bases installation on the light pole foundation on Maryland Avenue, inbound between 4th St and Mass Ave intersections.