Work along the Maryland Avenue NE corridor continues to make progress. In the last week the team accomplished the following:

  • Installed electrical duct bank, light pole foundation and manhole at Maryland Avenue NE at 11th and 8th St intersections

  • Installed a storm sewer inlet at Maryland Avenue NE and 9th St

  • Installed a storm sewer inlet at Maryland Avenue NE and 8th St


**Please note: The bus stop location at Maryland Ave NE and 8th St NE has been temporarily closed while work is being performed at that intersection. Please use the next bus stop to board the bus.