
Maryland Ave Community Information
Project Updates June 1-7, 2020
The weekly update will also include the two-week look ahead for both the DDOT and Washington Gas project. The work completed section will consist of work completed by the DDOT team only.
DDOT Two Week Look Ahead
Work on bump-outs, curb gutter, and sidewalk installation on Maryland Avenue NE, inbound between 13th St to G St.
Install PCC bus pad at Mass Avenue and 4th St intersection.
Install 20ft SL/TS poles on Maryland Ave between 2nd and 6th St.
Work on storm drains, inlets, and storm drain manholes installations on Maryland Avenue NE, outbound between 6th St and 8th St
Utility trench repairs on Maryland Avenue NE, between 2nd St and 4th St.
Washington Gas Two Week Look Ahead
Main abandonment work remains on Maryland Avenue between 6th Street NE & 13th Street NE. This work should be isolated and not affect many residents. (Crew 1 on the abandonment between 6th St. & Maryland Ave and 7th St & Maryland Ave.)
Continue excavations at the northeast corner of D St, 7th St & Maryland Ave.
Crew 2 is currently working on the main installation on the 1300 Block of Maryland Ave inbound.
The pavement restoration crew is anticipating starting trench repairs at 1300 block of Maryland Ave, outbound.
Work Completed June 1-7, 2020
Started demolition for the PCC bus pad granite curb installation on Maryland Ave inbound at 7th St.
Continued 28Ft SL/TS Poles installation on Maryland Ave between 14th St to 6th St.
Continued transfer to temporary poles on Maryland Ave between 2nd to 5th street.
Continued concrete encased electrical conduit duct bank and light pole foundations installation on Maryland Avenue around Stanton Park.
Continued PCC bus pad granite curb installation on Maryland Ave inbound at 7th St.
Continued bump‐outs and ramps installation at Maryland Ave and 14th St, inbound.
Performed PCC base repair over the utility trench on Avenue Maryland Avenue around Stanton Park