• Maryland Ave Community Information

Project Updates May 11-17, 2020



Progress along the Maryland Avenue NE Corridor included:

  • FMCC electrical crew transferred two traffic signal poles onto temporary concrete bases at onsite in the 2nd and Maryland Avenue. Removed two existing traffic signal poles.

  • · OMNI excavated and installed a 3 X 3 electrical manhole, excavated and poured one streetlight pole foundation, and installed two electrical duct banks ( MH-1.10 to MH-1.04 and MH-1.10 to SL-1.05) at 3rd Street and Constitution Avenue intersection. Completed the installation of the 18” PCC pipe between sewers MH-36 to MH-31

  • · OMNI completed the installation of the 18” PCC pipe between sewers MH-36 to MH-31 and started the excavation for the installation of the 18” PCC pipe between sewer manholes MH-36 to existing sewer manhole EX/MH-2. Backfilled and placed temporary asphalt as needed.

  • FMCC setup lane closures on WBL and EBL of MD Avenue NE, demolished existing median excavated subbase, placed base course and PCC base between the 7th street and 8th street intersections.

  • FMCC placed 2” asphalt over the PCC base trenches repair along the 11th street intersection between the proposed electric manhole MH 11.03 and MH 11.05 and at the median between the 8th and 9th streets intersections, stations: 33+36 to 31+87.

  • OMNI continued backfilling around sewer manhole MH-36 and placed 2-inches of temporary asphalt in the roadway. Backfilled the test pit location from the previous workday.

  • OMNI continued installation of the Basin Connect PCC Pipe Class III 15-Inch and concrete encased between sewer manhole MH-29 and inlet I-5. on Maryland Avenue between 3rd Street and 4th Street.

  • FMCC continued working on the bus stop pads installation at inbound Maryland Avenue near 11th St.

  • Omni continued PCC base installation over the lateral utility trenches crossing for the base repairs along inbound of the Maryland Ave NE between the 10th St and the 11th St. The crew prepared and poured concrete base on five trenches which are in between MH 9.07 – MH 9.01, MH 10.08-MH 10.06, and from the median towards the streetlight poles: RL 9.04. RL 10.07 and RL 10.02

  • OMNI continued backfilling and placed temporary asphalt over the electrical trenches and installed electrical MH-1.11 and completed 4-4” electrical duct bank installation between MH-1.10 and MH-1.11at the 3rd Street and Constitution Avenue intersection.

  • Omni formed and poured traffic pole foundation TS-7 and installed the electrical conduit duct bank between MH-1.11 and MH-1.12.

  • Omni completed the installation of the 18” PCC pipe between sewer manholes MH-36 to EX/MH-2. Backfilled the trench area and placed temporary asphalt as needed. Completed the entry seal in sewer manhole MH-36 and EX/MH-2.

  • FMCC resumed existing meridian demolition and PCC base placement between 6th and D street intersections

  • Omni continued PCC base installation over the six-lateral utility between MH 7.02 – MH 7.04, MH 8.06-MH 8.08, MH 8.08 - MH 8.02, and from the median towards the streetlight poles: RL 8.01. RL 7.07 and RL 7.05, RL 8.02 inbound of the Maryland Ave NE between the 8th St and the 7th St intersections.

  • OMNI continued backfilling, placing temporary asphalt, installation of electrical MH MH-1.12, the 1-2” and 1-4” duct bank between manhole MH-1.09 to TS-5 and the 1-2” and 1-4” duct bank between manhole MH-1.12 to TS-8 within the 3rd Street and Constitution Avenue.

  • Omni completed the installation and encasement of the 15” PCC pipe between sewer manhole MH-2 to inlet I-4 and EX/MH-5 to I-10. Performed the test pit for the installation of inlet I-11 within Stanton Park Circle.

  • FMCC continued existing meridian demolition and PCC base placement between 6th and D street intersections.

  • Omni placed 2” hot mix temporary asphalt over the PCC base repairs at inbound of the Maryland Ave NE between the 8th St and the 7th St intersections.

  • OMNI continued backfilling, placing temporary asphalt, installation of electrical the 1-2” and 1-4” duct bank between manhole MH-1.11 to MH-1.12, MH-1.09 to TS-5 (3rd & Con. Ave.), MH-1.12 to TS-8 (3rd & Con. Ave.)

  • Omni completed the trench backfill for the 15” PCC pipe between sewer manhole MH-2 to inlet I-4 and EX/MH-5 to I-10. Started the construction of the brick finish in sewer manhole MH-2 and MH-36 and completed the entry seal in both manholes along Maryland Avenue between 3rd Street and 4th Street

13 views